Question: 1 1 . Once construction begins, changes are difficult and expensive given the overlapping schedule in this project delivery method: a . Owner / Contractor

11. Once construction begins, changes are difficult and expensive given the overlapping schedule in this project delivery method:
a. Owner/Contractor
b. Design/bid/build
c. Design/Build
d. CM at risk