Question: 1 1 . Once construction begins, changes are difficult and expensive given the overlapping schedule in this project delivery method: a . Owner / Contractor
Once construction begins, changes are difficult and expensive given the overlapping schedule in this project delivery method:
a OwnerContractor
b Designbidbuild
c DesignBuild
d CM at risk