Question: 1 1 Problem 1 : Electronics Assembly Line An electronics factory assembles circuit boards with the following tasks: Task Time ( min ) Immediate Predecessor

11 Problem 1: Electronics Assembly Line
An electronics factory assembles circuit boards with the following tasks:
Task Time
(min)
Immediate
Predecessor(s)
A 3.2
B 2.1 A
C 1.8 A
D 4.0 B, C
Additional Information:
Target: 150 circuit boards in an 8-hour shift (480 minutes).
Optimize the production line to use the minimum number of workstations.
Tasks:
a) Calculate the cycle time required to meet the production goal. Round to two
decimal places.
b) Determine the minimum number of workstations needed within the cycle time.
2 Problem 2: Furniture Manufacturing
A furniture factory produces chairs with the following tasks:
Task Time
(min)
Immediate
Predecessor(s)
A 5.0
B 3.5 A
C 2.8 A
D 4.2 B
E 3.0 C, D
Additional Information:
Target: 100 chairs in a 10-hour shift (600 minutes).
Optimize the production line to use the minimum number of workstations.
Tasks:
a) Calculate the cycle time required to meet the production goal. Round to two
decimal places.
b) Determine the minimum number of workstations needed within the cycle time.
3 Problem 3: Toy Production Line
A toy factory manufactures dolls with the following tasks:
Task Time
(min)
Immediate
Predecessor(s)
A 2.5
B 1.9 A
C 3.3 A
D 2.7 B, C
Additional Information:
Target: 200 dolls in a 7-hour shift (420 minutes).
Optimize the production line to use the minimum number of workstations.
Tasks:
a) Calculate the cycle time required to meet the production goal. Round to two
decimal places.
b) Determine the minimum number of workstations needed within the cycle time.
4 Problem 4: Automotive Parts Assembly
An automotive factory assembles car components with the following tasks:
Task Time
(min)
Immediate
Predecessor(s)
A 4.5
B 2.0 A
C 3.8 A
D 5.1 B
E 2.9 C, D
Additional Information:
Target: 90 components in a 9-hour shift (540 minutes).
Optimize the production line to use the minimum number of workstations.
Tasks:
a) Calculate the cycle time required to meet the production goal. Round to two
decimal places.
b) Determine the minimum number of workstations needed within the cycle time.
5 Problem 5: Packaging Line
A packaging facility prepares boxes with the following tasks:
Task Time
(min)
Immediate
Predecessor(s)
A 1.5
B 2.2 A
C 1.8 A
D 3.0 B, C
E 2.5 C
Additional Information:
Target: 180 boxes in an 8-hour shift (480 minutes).
Optimize the production line to use the minimum number of workstations.
Tasks:
a) Calculate the cycle time required to meet the production goal. Round to two
decimal places.
b) Determine the minimum number of workstations needed within the cycle time.
6 Problem 6: Food Processing Line
A food processing plant prepares meals with the following tasks:
Task Time
(min)
Immediate
Predecessor(s)
A 3.0
B 2.5 A
C 4.0 A
D 3.2 B
E 2.8 C, D
Additional Information:
Target: 120 meals in a 6-hour shift (360 minutes).
Optimize the production line to use the minimum number of workstations.
Tasks:2
a) Calculate the cycle time required to meet the production goal. Ro
1 1 Problem 1 : Electronics Assembly Line An

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!