Question: 1 1 . _ _ _ _ processes include coordinating people and other resources to carry out project plans and create the products, services, or
processes include coordinating people and other resources to carry out project plans and create the products, services, or results of the project or phase
Points
Initiating
Planning
Executing
Monitoring and Controlling
Closing
Which process group normally requires the most resources and time?
Points
Initiating
Planning
Executing
Monitoring and Controlling
Closing
A work breakdown structure, project schedule, and cost estimates are outputs of the process
Points
Initiating
Planning
Executing
Monitoring and Controlling
Closing
involves measuring progress toward project objectives and taking corrective actions.
Points
Initiating
Planning
Executing
Monitoring and Controlling
Closing
Initiating involves developing a project charter, which is part of the project management knowledge area.
Points
integration
scope
communication
risk
Many people use to have a standard format for preparing various project management documents
Points
methodologies
templates
project management software
standards
A new government law requires an organization to report data in a new way. Which of the following categories would include a new information system project to provide this data?
Points
Problem
Opportunity
Directive
Regulation
A is a document that formally recognizes the existence of a project and provides direction on the project's objectives and management.
Points
project charter
contract
business case
project management plan
What tool and technique is used for all processes of project integration management?
Points
Project management software
Templates
Expert Judgement
All of the above
A is a deliverableoriented grouping of the work involved in a project that defines its total scope
Points
scope statement
WBS
WBS dictionary
work package
Scope is often achieved by a customer inspection and then signoff on key delvierables.
Points
accetamce
validation
completion
closeout
Which tool or technique for collecting requirements is often the most expensive and time consuming?
Points
Interviews
Focus groups
Surveys
Observation
As the project manager for a software development project, you are helping to develop the project schedule. You decide that writing code for a system should not start until users sign off on the analysis work. What type of dependency is this?
Points
Technical
Mandatory
Discretionary
External
What type of diagram shows planned and actual project schedule informaiton?
Points
A network diagram
A Gantt chart
A Tracking Gantt chart
A milestone chart
is a network diagramming technique used to predict total project duration.
Points
PERT
A Gantt chart
Critical path method
Crashing
You cannot start editing a technical report until someone else completes the first draft. What type of dependency does this represent?
Points
Finishtostart
Starttostart
Finishtofinish
Starttofinish
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock