Question: 1. (11). Using the schedule from Chapter 5, estimate the cost for each activity, (10 possible points) If using Microsoft Project (note: the use of

 1. (11). Using the schedule from Chapter 5, estimate the cost
for each activity, (10 possible points) If using Microsoft Project (note: the

1. (11). Using the schedule from Chapter 5, estimate the cost for each activity, (10 possible points) If using Microsoft Project (note: the use of Microsoft Project is not required), enter the rates of the work and material resources on the Resource Sheet. Assign the cost resource amount on the Task Information window for the task where the resource is assigned. Any resources that are not assigned for the duration of a work package should have a percent of effort assigned. Or the task should be changed to a fixed duration and the amount of work changed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!