Question: 1 2 : 0 1 1 2 : 0 1 sidebar interaction. Press tab to begin. A network consists of the following list. Times are

12:01
12:01
sidebar interaction. Press tab to begin.
A network consists of the following list. Times are given in weeks.
Activity
Preceding
Optimistic
Probable
Pessimistic
A
--
5
11
14
B
--
3
3
9
C
--
6
10
14
D
A, B
3
5
7
E
B
4
6
11
F
C
6
8
13
G
D, E
2
4
6
H
F
3
3
9
(b) Calculate the expected duration and variance of each activity.
(c) Calculate the expected duration and variance of the critical path