Question: 1 2 : 0 1 1 2 : 0 1 sidebar interaction. Press tab to begin. A network consists of the following list. Times are
:
:
sidebar interaction. Press tab to begin.
A network consists of the following list. Times are given in weeks.
Activity
Preceding
Optimistic
Probable
Pessimistic
A
B
C
D
A B
E
B
F
C
G
D E
H
F
b Calculate the expected duration and variance of each activity.
c Calculate the expected duration and variance of the critical path