Question: 1 2 , 1 point You are the project manager of an IT project that's scheduled for 1 8 months with a Budget at Completion

12,1 point
You are the project manager of an IT project that's scheduled for 18 months with a Budget at Completion (BAC) of $900,000. Currently, you're in month 9, and the project has incurred an Actual Cost (AC) of $500,000. The project was planned to be 60% complete by this point, but upon reviewing the deliverables, you ascertain that only 50% of the work has been finished.
Using Earned Value Management (EVM), calculate the Cost Variance (CV), Schedule Variance (SV), and determine the most likely scenario regarding the project's performance.
CV: -$10,000,SV:-$0,000, the project is slightly over budget and behind schedule; r r w mmend a slight increase in pace.
CV:-$50,000,SSV:$90,000, the project is over budget and behind schedule; reassess project resource allocation and timeline.
CV:$10,000,SV:$50,000, the project is under budget and slightly ahead of schedule; proceed as planned with regular monitoring.
CV:$50,000,SV:$90,000, the project is under budget and ahead of schedule; advise the team to maintain the pace.
 12,1 point You are the project manager of an IT project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!