Question: 1 2 , 1 point You are the project manager of an IT project that's scheduled for 1 8 months with a Budget at Completion
point
You are the project manager of an IT project that's scheduled for months with a Budget at Completion BAC of $ Currently, you're in month and the project has incurred an Actual Cost AC of $ The project was planned to be complete by this point, but upon reviewing the deliverables, you ascertain that only of the work has been finished.
Using Earned Value Management EVM calculate the Cost Variance CV Schedule Variance SV and determine the most likely scenario regarding the project's performance.
CV: $:$ the project is slightly over budget and behind schedule; r r w mmend a slight increase in pace.
:$:$ the project is over budget and behind schedule; reassess project resource allocation and timeline.
:$:$ the project is under budget and slightly ahead of schedule; proceed as planned with regular monitoring.
:$:$ the project is under budget and ahead of schedule; advise the team to maintain the pace.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
