Question: 1 2 3 4 5 6 7 242 60 Table Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Releases 21 1

1 2 3 4 5 6 7 242 60 Table Gross Requirements

1 2 3 4 5 6 7 242 60 Table Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Releases 21 1 2 3 4 5 6 7 33 Legs (4 per table) Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Releases 34 ? The tables you produce are made of one table top and four legs per table. The above shows current state. Tables have a three week lead time, and legs have a two week lead time. What quantity is planned for release in week 2 for table legs? Type your