Question: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 8. Consider the processing times and due

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 8. Consider the processing times and due dates of the following jobs: Job Processing time (days) Due date 3 35 19 (days) 25 24 40 8 20 What is the tardiness of job 4 If earliest due date is used to sequence the jobs? OX