Question: 1 2 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 A Moving to another question
1 2 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 A Moving to another question will save this response. Question 16 (CH2) Who authorizes the project? a. Functional manager of the department where project will be performed b. CEO of the organization c Project sponsor d. Project sponsor and project manager Moving to another question will save this response. MacBook Pro esc 20 F3 889 F2 Tied Test This test has a time limit of hour This test will be and submit automatically when the time expres Warnings appear when half the time, 5 minutes, 1 minute, and 30 seconds remain Multiple Attempts Thistest allows 2 temps. This is attempt number 1 Force Completion Once started this test must be completed in one sitting. Do not leave the test before clicking Save and Submit Remaining Time: 57 minutes, 28 seconds. Question Completion Status: 1 2 3 10 12 14 15 Moving to another question will save this response. Question 17 of 30 >>> Question 17 1 points (CHS) it's important for you, the project manager, to understand what each of the project management processes creates. One of the key processes you'll do is scope control throughout your project. Which of the following is an output of scope control Workaround b. None of the given answers Transference d. Risk assessment MacBook Pro 888 5 Warnings appear when half the time, 5 minutes, 1 minute, and 30 seconds remain, Multiple Attempts This test allows 2 attempts. This is attempt number 1 Force Completion Once started this test must be completed in one sitting Do not leave the test before clicking Save and Submit Remaining Time: 57 minutes, 22 seconds. Question Completion Status: 1 2 10 11 12 13 14 15 17 16 18 19 21 26 22 30 27 Moving to another question will save this response Question 18 of 30 Question 18 3 points (CHI) You are being interviewed by a functional manager, who says. "We have this huge undertaking of launching an online education website that contains different components, such as designing the website, developing the content, developing the administrative system including registration and payment, marketing the courses on the website, integrating different components of the website, and finally going live. Each component is functionally complex and large enough that it will be better served under a different management." The manager is most likely describing a a. Project b. Program c. Operation d. Portfolio MacBook Pro BO 888 Tined Test This test has a time limit of 1 hour. This test will save and submit automatically when the time expires. Warnings appear when half the time 5 minutes, 1 minute, and 30 seconds remain Multiple Attempts This test allows 2 attempts. This is attempt number 1 Force Completion Once started this best must be completed in one sitting Do not leave the test before clicking Save and Submit Remaining Time: 57 minutes, 17 seconds. Question Completion Status: 24 25 26 23 22 28 29 30 21 9 7 13 14 2 10 4 11 15 17 5 12 16 Moving to another question will save this response Question 19 of 30 Question 19 3 points Save Are ICHS) You've been asked to start the process of creating the project scope statement and you need to gather the elements for this process. Which one of the following is not needed to define the project scope? a. A project charter b. Organizational process assets Arisk management plan d. Requirements documentation MI MacBook Pro DHE