Question: 1 2 5 Question 1: 11 marks) For the project detailed in the table below: a) Draw the Activity on Node (AoN) network diagram using

1 2 5 Question 1: 11 marks) For the project detailed in the table below: a) Draw the Activity on Node (AoN) network diagram using labels for activity node showing early start, late start, early finish, late finish, and the slack time b) Run the forward pass (4.5 marks) c) Run the backwards pass (4.5 marks) d) Calculate the total slack time in the network (1 mark) e) Identify the critical path (1 mark) Activity Preceding Activity Time (Weeks) None 7 B None 8 None 6 D 6 E B 6 F B 8 G 4 H DE 7 1 F,G,H 3 000 HE B