Question: 1. 2. A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are as follows: Activity Immediate Predecessors Activity
1. 
2.
A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are as follows:
| Activity | Immediate Predecessors | Activity Time |
| A | | 3 |
| B | | 7 |
| C | A | 3 |
| D | B, C | 2 |
| E | C, D | 5 |
| F | E | 2 |
| G | B | 10 |
| H | F, G | 2 |
Choose the correct network for the project.
The correct network is: network A, network B, network C, network D
Choose the correct early-start-date Gantt chart for the computer-system installation project.
The correct Gantt chart is: chart A, chart B, chart C, chart D
What are the critical path activities?
The critical path is: -A-C-D-E-F-H, B-D-E-F-H, A-C-E-F-H, B-G-H
What is the project completion time? Round your answer to the nearest whole number.
______ weeks
3. 
A competitor or Kozar International Inc. has begun marketing a new, instant developing film project. Kozar has had a similar product under study in its research and development (R&D) department but has not yet been able to begin production. Because of the competitor's action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are as follows: Immediate Optimistic Most Pessimistic Activity Predecessors Time Probable Time Time A 2 2.5 B A 4 5 6 A 3 4 D B, C 1.5 6 7,5 E 3 4.5 9 F 7.5 12.5 F 11.5 14 a. Choose the correct network for the project The correct network is -Select- B. B b. Develop an activity schedule for this project using early and late start and finish times and compute activity slack time. If your answer is zero, enter "o". Round your answers to the nearest whole number. Latest Immediate Time Earliest Earliest Latest Activity Predecessors (months) Start Finish Start A Finish Slack C D B, C E B F C, D, E F Define the critical activities. The critical path is -Select- Environment Recycling Inc must dean up a large automobile tire cump under a state environmental cleanup contract. Suppose that some of the activities in the Environment Recycling Inc. Situation can be crashed. The following table shows the crash times and costs associated with performing the activities at their original (normal) times and also for the cresh times. Immediate Normal Time Crash Time Normal Cost Crash Cest Activity Predecessore 4 3 2 $480 B A 4 2 1,750 $630 2,350 1,060 C 9 3 2 H6D D 720 870 E 6 5 1,900 F D 3 2 120 520 D 4 2,150 1,070 1,020 700 1,450 5 4 500 H 1 E F,G,H 4 2 850 a. Choose the correct network for the project The correct network is -Select- A E. B . D. b. Identify the critical path. The critical path is -Select- L. What is the total project completion time? Round your answer to the nearest whole number. weeks d. What is the lowest cost solution in the state wants to complete the project three weeks early7 Round your answer for the project duration to the nearest whole number and the answer for the total cost to the nearest dollar The total cost of acan) week praject completion schedule is $