Question: 1 . 2 A town s council has established a project proposal team to select a project to improve local services for their citizens. Use

1.2 A towns council has established a project proposal team to select a project to improve local services for their citizens. Use a weighted scoring model to analyze three possible projects (A, B, C) for improving their services. The relative weights for each criterion are shown in the following table. A score of 1 represents unfavorable, 2 satisfactory, and 3 favorable.
Project
Success Factor
Weight
A
B
C
Project cost
20
1
2
3
Timely completion
20
2
3
1
Service quality
10
2
1
3
Contractor relations
10
3
3
2
Affordability
10
2
1
1
Citizen satisfaction
25
1
2
3
County relations
5
2
2
2
1.3
Compare your answer in Exercise 1.2 to the answer you would have found if you had used an unweighted, 0-1 scoring model. Assume that a score of 1 means does not qualify and a 2 or 3 means it does qualify.
Next, revise the unweighted model by deleting all success factors that, as recommended, have a weight of less than 20 percent. Compare to your answer to (a) above and also Exercise 1.2. Which method seems best?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To approach this problem using a weighted scoring model we need to follow these steps Step 1 Identify the Criteria and Weights The criteria along with ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!