Question: 1 2 . AdventureLand theme park recently received a large number of complaints from customers who had endured delays while waiting to ride on AdventureLand

12. AdventureLand theme park recently received a large number of complaints from customers who had endured delays while waiting to ride on AdventureLands largest rollercoaster, Monster Train. As newly appointed operations manager, you are considering the problem of delayed rides on Monster Train. By observing 150 delayed Monster Train rides over a 12 week period, you find that a variety of factors are contributing to the Monster Train delay problem. You summarize the results of your study in a diagram:
MONSTER TRAIN OPERATION
RIDE DELAY
WAITING AREA PERSONNEL
You also create this table to tally the frequency with which you observed various causes of delay:
Problem Areas Number of Occurrences
Delayed availability of safety inspector 2
Mechanical failure of turnstile 17
Broken gearing mechanism requiring repair 15
Staff arrive late for work 43
Bad weather 2
Insufficient staff to load passengers 21
Please answer the following questions, based on this information.
a. Pareto analysis would suggest that AdventureLand theme park focus on which two Monster Train problem areas first? (2 points)
b. Insufficient Staff to load passengers is categorized in the fishbone diagram under what main heading? (1 point)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!