Question: 1 . 2 An assembly line is shown in Figure 1 . The process B occurs separately but simultaneously with the Process C , while

1.2 An assembly line is shown in Figure 1. The process B occurs separately but simultaneously with the Process C, while process E has three identical machines in parallel. All operations are done manually. One operator is assigned to each machine.
Figure 1: Processes in an assembly line
a) If the firm operates 8 hours per day, 20 days per month, determine bottleneck station and theoretical monthly capacity of the assembly line.
(3 marks)
b) The company received customer orders in average of 2500 units per month. Determine how many assembly lines have to setup to fulfil the demand.
(1 mark)
c) Determine the percentage of efficiency if the actual output of this assembly line is 850 units per month per assembly line.
(1 mark)
 1.2 An assembly line is shown in Figure 1. The process

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!