Question: 1 . 2 . Based on your grouping above, please list work elements for each workstation. table [ [ Work Station # 1 ,

1.2. Based on your grouping above, please list work elements for each workstation.
\table[[Work Station #1,Work Station #2,Work Station #3,Work Station #4],[,,,],[A-50,B-30,D-45,G-10],[C-20,E-20,F-25,H-35],[,,,]]
1.3. Based on your grouping above and the cycle time of 72 seconds,
-what is the sum of task time for the line you have created?
-what is the total amount of idle time in this production line you have created?
-what is the efficiency of this production line you have created?
 1.2. Based on your grouping above, please list work elements for