Question: 1 2 . Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $ 2

12. Janet is forecasting how much money her department needs to support a new project. She
estimates that two people and $25,000 in expenses will cover her needs. Because
management typically insists on reducing forecasts by 20 percent, she increases her
estimates to allow for that reduction. Which of the following factors is illustrated in this
situation?
A. Padding estimates
B. Planning horizon
C. Project structure
D. People
E. Organization culture
13. Which of the following is provided by a project network but not by the work breakdown
structure?
A. Dependencies
B. Sequencing
C. Interrelationships
D. Both A and B are correct
E. A, B, and C are all correct
14. On a project network, the activity times are derived from the
A. Organization breakdown structure
B. Work packages
C. Budget
D. Project proposal
E. Responsibility matrix
15. An activity that has more than one dependency arrow flowing into it is termed a(n)
A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity
16. An uncertain event or condition that, if it occurs, has a positive or negative effect on a
project objectives is termed.
A. Random chance
B. A disaster

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!