Question: ( 1 2 Tasks to 4 Workers ) Consider the following tasks that must be assigned to four work - ers on a conveyor -

(12 Tasks to 4 Workers) Consider the following tasks that must be assigned to four work- ers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There is unlimited demand.
Time to Complete Task (seconds)
Task 130 Task 225 Task 315 Task 420 Task 515 Task 620 Task 750 Task 815 Task 920 Task 1025 Task 1115 Task 1220
The current conveyor-paced assembly-line configuration assigns the workers in the following way:
Worker 1: Tasks 1,2,3
Worker 2: Tasks 4,5,6
Worker 3: Tasks 7,8,9
Worker 4: Tasks 10,11,12
What is the capacity of the current line?
What is the direct labor content?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!