Question: 1 3 . 2 1 Suppose, for Problem 1 3 . 2 0 , that your PV was 7 0 and your EV was 9

13.21 Suppose, for Problem 13.20, that your PV was 70 and
your EV was 95. Recalculate the SPI and estimated time
to completion for the project with this new data.