Question: ( 1 3 pts ) An order for 2 0 0 bolts is procesed on work centers 1 and 2 . The setup and run

(13 pts) An order for 200 bolts is procesed on work centers 1 and 2. The setup and run times are as follows. It is decided to overlap the lot on the two work centers and to split the lot into two lots. 30 mlease assume that the transfer lots are found using lot formulation. Move time between operations is 30 minutes, Work center 2 cannot be set up until the first lot arrives.
Setup on A=50 minutes
Run time on A=5 minutes per piece
Setup onB=100 minutes Run time onA=5 minutes per piece
Run time onB=7 minutes per piece
200 units q,
q,Tra
u fer Machine B
(a)(5) Calculate the manufacturing lead time before dverlapping.
b)(8) Calculate the manufacturing lead time after overlapping and saving in manufacturing lead time.
T1=QTRTA-SUBRTA+RTB,T2=QT-T1
 (13 pts) An order for 200 bolts is procesed on work

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!