Question: 1 . 3 pts q , is an iterative method in which resources are allocated to activities based on the least slack. q , Resource

1.3 pts
q, is an iterative method in which resources are allocated to activities based on the least slack.
q,
Resource evaluation scheduling
Resource monitoring
Resource leveling