Question: 1 3 . The method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within
The method used to estimate the minimum project duration and determine the amount of
scheduling flexibility on the logical network paths within the schedule model is called the
a Gantt chart method
b Critical path method
c PERT method
d Critical chain method