Question: 1 3 . The method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within

13. The method used to estimate the minimum project duration and determine the amount of
scheduling flexibility on the logical network paths within the schedule model is called the
______________.
a) Gantt chart method
b) Critical path method
c) PERT method
d) Critical chain method