Question: 1 : 4 0 PM Mon Sep 3 0 1 9 % Back FARE 3 3 1 0 - Fal 1 : Assignment 1 (

1:40 PM Mon Sep 30
19%
Back
FARE3310- Fal1: Assignment 1
(30 points) An advertising agency CEO has gathered the activity information for a new advertising campaign as shown in the accompanying table.
\table[[Activity,Time estimate weeks],[Optimistic,Most Likely,Pessimistic,\table[[Immediate],[Predecessors]]],[A,2,5,8,-],[B,2,6,7,-],[C,3,3,6,B],[D,7,14,15,A],[E,3,6,12,A,C],[F,6,8,16,B],[G,2,6,7,E,F]]
a) Draw the network diagram. What is the expected completion time (state it explicitly)? What is the variance of project completion time?
b) The deadline is 23 weeks. What is the probability of completing it on time? What is the probability of the project missing the deadline?
c) As project manager, you will be paid a bonus if you finish the project in 19 weeks. What is the probability of achieving the bonus?
d) What is the probability of finishing between 19 and 23 weeks?
e) What is the timeline that would achieve a 60% probability of finishing?
 1:40 PM Mon Sep 30 19% Back FARE3310- Fal1: Assignment 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!