Question: 1 ) ( 4 0 points ) You and several friends are about to prepare a lasagna dinner. The tasks to be performed, their immediate
points You and several friends are about to prepare a lasagna dinner. The tasks to be performed, their immediate predecessors, and their estimated durations are as follows:
activity
description
immediate predecessors
estimated duration min
A
buy the mozzarella cheese
slice the mozzarella
A
beat eggs
D
mix eggs and ricotta cheese
E
cut up onions and mushrooms
F
cook the tomato sauce
E
G
boil large quantity of water
boil the lasagna noodles
G
I
drain the lasagna noodles
H
J
assemble all the ingredients
F D B
K
preheat the oven
L
bake the lasagna
I, K
Draw a project network representing the preparation of the lasagna.
When can the individual activities start and finish at the earliest if no delays occur?
What is the total time required to make the lasagna if no delays occur? min When do the individual activities need to start and finish at the latest to meet this completion time?
Which are the critical bottleneck activities where delays must be avoided to prevent delaying the completion of the lasagna? A B JL
For the other activities, how much delay can be tolerated without delaying the completion of the lasagna?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock