Question: 1 ) ( 4 0 points ) You and several friends are about to prepare a lasagna dinner. The tasks to be performed, their immediate

1)(40 points) You and several friends are about to prepare a lasagna dinner. The tasks to be performed, their immediate predecessors, and their estimated durations are as follows:
activity
description
immediate predecessors
estimated duration (min)
A
buy the mozzarella cheese
30
slice the mozzarella
A
5
beat 2 eggs
-
2
D
mix eggs and ricotta cheese
3
E
cut up onions and mushrooms
7
F
cook the tomato sauce
E
25
G
boil large quantity of water
15
boil the lasagna noodles
G
10
I
drain the lasagna noodles
H
2
J
assemble all the ingredients
1, F, D, B
10
K
preheat the oven
15
L
bake the lasagna
I, K
30
(0,30)/
30
0,30
Draw a project network representing the preparation of the lasagna.
When can the individual activities start and finish (at the earliest) if no delays occur?
What is the total time required to make the lasagna if no delays occur? 75 min When do the individual activities need to start and finish (at the latest) to meet this completion time?
Which are the critical bottleneck activities where delays must be avoided to prevent delaying the completion of the lasagna? A, B / J,L
For the other activities, how much delay can be tolerated without delaying the completion of the lasagna?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!