Question: 1 4 1 . 5 points Slutzer supplies components for a specialized type of motherboard, with an estimated theoretical cycle time of 1 8 0

141.5 points
Slutzer supplies components for a specialized type of motherboard, with an estimated theoretical cycle time of 180 seconds per part. The machinery used runs for a total of 8.5 hours. Within this timeframe, it manufactured 155 parts, three of which were defective. Calculate the Overall Equipment Effectiveness.
81.07
89.41
77.21
63.27
67.23