Question: 1 4 . 3 The demand for subassembly ( S ) is 1 0 0 units in week 7 . Each unit of
The demand for subassembly S is units in week
Each unit of requires unit of T and units of U Each unit of T requires unit of V units of W and unit of X Finally, each unit of U requires units of Y and units of Z One firm manufactures all items. It takes weeks to make mathrmS week to make T weeks to make U weeks to make V weeks to make mathrmW week to make X weeks to make X and week to make Z
a Construct a product structure. Identify all levels, parents, and components.
b Prepare a timephased product structure.