Question: 1 4 . 3 The demand for subassembly S is 1 0 0 units in week 7 . Each unit of S requires 1 unit

14.3 The demand for subassembly S is 100 units in week 7.
Each unit of S requires 1 unit of T and 2 units of U. Each unit of
T requires 1 unit of V,2 units of W, and 1 unit of X. Finally, each
unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T,
2 weeks to make U,2 weeks to make V,3 weeks to make W,1 week
to make X,2 weeks to make Y, and 1 week to make Z.
K(1)
L(4) M(2)
J
* Note: PX means the problem may be solved with POM for Windows
and/or Excel OM. Many of the exercises in this chapter (14.1 through 14.16
and 14.23 through 14.27) can be done on Resource Manager for Excel, a
commercial system made available by User Solutions, Inc. Access to a trial
version of the software and a set of notes for the user is available at
www.usersolutions.com.
a) Construct a product structure. Identify all levels, parents, and
components.
b) Prepare a time-phased product structure.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!