Question: 1 4 ) Question ID: 5 3 5 You have been assigned as the project manager for a construction project that has had two previous
Question ID: You have been assigned as the project manager for a construction project that has had two previous project managers, when you discover a deliverable will be late.Your analysis shows the item can be purchased from another seller at a higher price without affecting the schedule. What is the best thing to doACrash or fast track the project.B Change the project management plan to reflect the new due date.CDEvaluate the impact of the decision.Discuss the impact with the customer and ask for a decision.