Question: 1 4 . The fictitious Cool Air Inc, assembles three models ( A , B , and C ) of air conditioners. The production manager

14. The fictitious Cool Air Inc, assembles three models (A, B, and C) of air conditioners. The production manager at the Cool Air plant wants to implement uniform production and mixed-model scheduling. The company has demand forecasts for 600 units of Model A,400 for Model B, and 100 units for Model C next month. The plant operates 25 days per month and has the capacity to produce 200 air conditioners per day.
a. If a mixed-model production schedule is used, what assembly sequence would the production manager use?
b. How many times per day would the assembly sequence be repeated?