Question: 1 5 : 2 5 . l LTE Assignment 1 ( 2 ) Question 1 The Airforce of Zimbabwe Aircraft Co . is ready to
:
l LTE
Assignment
Question
The Airforce of Zimbabwe Aircraft Co is ready to begin a project to develop a new fighter airplane for the Zimbabwean Air Force. The company's contract with the Department of Defense calls for project completion within I weeks, with penalties imposed for late delivery. The project involves activities labeled dots, where their precedence relationships are shown in the following project network.
Using the PERT threeestimate approach, the usual three estimates of the duration of each activity have been obtained as given below.
tableActivitytableOptimisticEstimatetableMost LikelyEstimatetablePessimisticEstimateA weeks, weeks, weeksB weeks, weeks, weeksC weeks, weeks, weeksD weeks, weeks, weeksE weeks, weeks, weeksF weeks, weeks, weeksC weeks, weeks, weeksH weeks, weeks, weeksI weeks, weeks, weeks weeks, weeks, weeks
a Find the estimate of the mean and variance of the duration of each activity.
b Find the mean critical path.
c Find the approximate probability that the project will finish within weeks.
c Find the approximate probability that the project will
d Is the approximate probability obtained in part c likely to be higher or lower than the true value?
CS
CamScanner
Question
abel each of the following statements about the PERI threeestimate approach as true or false, and then justify your answer
a Activity durations are assumed to be no larger than the optimistic estimate and no smaller than the pessimistic estimate.
b Activity durations are assumed to have a normal distribution.
c The mean eritical path is assumed to always require the minimom
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock