Question: 1 5 : 2 5 . l LTE Assignment 1 ( 2 ) Question 1 The Airforce of Zimbabwe Aircraft Co . is ready to

15:25
.l LTE
Assignment 1(2)
Question 1
The Airforce of Zimbabwe Aircraft Co. is ready to begin a project to develop a new fighter airplane for the Zimbabwean Air Force. The company's contract with the Department of Defense calls for project completion within I00 weeks, with penalties imposed for late delivery. The project involves 10 activities (labeled A,B,dots,J), where their precedence relationships are shown in the following project network.
Using the PERT three-estimate approach, the usual three estimates of the duration of each activity have been obtained as given below.
\table[[Activity,\table[[Optimistic],[Estimate]],\table[[Most Likely],[Estimate]],\table[[Pessimistic],[Estimate]]],[A,28 weeks,32 weeks,36 weeks],[B,22 weeks,28 weeks,32 weeks],[C,26 weeks,36 weeks,46 weeks],[D,14 weeks,16 weeks,18 weeks],[E,32 weeks,32 weeks,32 weeks],[F,40 weeks,52 weeks,74 weeks],[C,12 weeks,16 weeks,24 weeks],[H,16 weeks,20 weeks,26 weeks],[I,26 weeks,34 weeks,42 weeks],[/,12 weeks,16 weeks,30 weeks]]
(a) Find the estimate of the mean and variance of the duration of each activity.
(b) Find the mean critical path.
(c) Find the approximate probability that the project will finish within 100 weeks.
10
(c) Find the approximate probability that the project will
5
(d) Is the approximate probability obtained in part (c) likely to be higher or lower than the true value?
1
CS
CamScanner
Question 2
_abel each of the following statements about the PERI three-estimate approach as true or false, and then justify your answer
a) Activity durations are assumed to be no larger than the optimistic estimate and no smaller than the pessimistic estimate. 2
b) Activity durations are assumed to have a normal distribution.
c) The mean eritical path is assumed to always require the minimom
[2]
 15:25 .l LTE Assignment 1(2) Question 1 The Airforce of Zimbabwe

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!