Question: 1 5 . 2 A company assembles three distinct finished SKUs, items F 1 , F 2 , and F 3 . The bills of

15.2 A company assembles three distinct finished SKUs, items F1, F2, and F3. The bills of materials for these items, their components, and quantities, are as follows:
Item FL: Composed of 1 unit of A1, A2, and A3 and 2 units of A4
Item F2: Composed of 1 unit of A1, A2, and A4
Item F3: Composed of 1 unit of Al and A4
Item A1: Composed of 1 unit of A2 and BI
Item A2: Composed of 1 unit of A4, B1, and B2
Item A3: Composed of 1 unit of \( B 1\) and \( B 2\) and 3 units of B3
Item A4: Composed of 2 units of B3
Item BL: Composed of 1 unit of B3 and Cl
Item B2: Composed of 1 unit of C1 and C2
Item B3: Composed of 1 unit of C1, C2, and C3
Items C1, C2, and C3 are purchased parts. In addition, items Al and A 2 are sold directly to customers as spare parts.
Develop a level-by-level coding for the thirteen items.
15.3 Suppose that the offects for the operations involved in Problem 15.2 are as follows:
Considering only F1 and its components,
a. What minimum horizon should be used for the master production schedule?
b. If the only customer order is for 10 units of item F1 in week 15 and there is no initial on-hand or on-order stock for any items, establish the procure ment and production schedule for item F1 and all its components.
1 5 . 2 A company assembles three distinct

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!