Question: 1 5 7 9 Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings(Enter your responses as

1 5 7 9 Shown below is a partially completed MPS
1 5 7 9 Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings(Enter your responses as integers. A response of *o* is equivalent to being not applicabile) Item: Ball bearings Order Policy: 500 units Lend Time: 1 week Quantity Week on Hand: 400 2 3 4 6 8 Forecast 550 250 450 500 300 300 250 350 500 Customer orders 300 350 250 300 250 200 50 150 50 (booked) Projected on-hand 350 D inventory MPS quantity 500 10 350 150 D D JO