Question: 1 . 5 For any two activities in a project to be fast tracked in relation to each other, there are two practical conditions that

1.5 For any two activities in a project to be fast tracked in relation to each other, there are two practical conditions that must both be satisfied. If neither of these conditions are met, then the activities cant be executed concurrently. Name these two conditions and, with reference to the scenario, create an example for each condition to demonstrate your understanding of their practical application. Be sure to focus on the fast tracking conditions for two activities and not two projects. (Max.4 lines per condition)