Question: [ 1 5 points ] A forensic analysis lab received eight forensic analysis jobs. The processing time for each job and the expected due date
points A forensic analysis lab received eight forensic analysis jobs. The processing time for each job and the expected due date for each job are as follows:
tableJobProcessing Time minutestableDue Date minutes fromthe start time
a Assume that all jobs are available to start at time Calculate and compare the average flowtime, lateness, and tardiness for the following sequencing rules:
i Process in the order they have arrived First come first serve
ii Shortest processing time
iii. Earliest due date
b If you want to minimize the largest latenesstardiness which sequencing rule is best? Explain using the results in a