Question: ( 1 . 5 points, and two long problems ( 4 . 5 points ) . But Question 7 3 A contingency reserve is used

(1.5 points, and two long problems (4.5 points). But
Question 73
A contingency reserve is used for-
Risks that are not identified at the outset of the project but are known before they occur
Risks that use a contingent response strategy
Risk for which the avoid strategy is used
Risks for which the accept response is selected