Question: ( 1 5 points ) Consider an end - item product C with the following master schedule and product structure tree: Other in
points Consider an enditem product C with the following master schedule
and product structure tree:
Other in
a One is made up of and
b The assembly of A and B to make C is one week.
c The part A is made by the company and lead time is two weeks.
d The part is made by the company and lead time is one week.
eC follows a lotforlot policy. The company follows a lotsize ordering policy for both
A and B with lot size of for A and for B
f There is a scheduled receipt for B at the beginning of week
g There are units of C on hand prior to period and units on hand for A and B
prior to period
On the next page, explode out the MRP schedule and fill in all cells of the schedule which
would have nonzero values.
ITEM C
ITEM A
ITEM B
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock