Question: 1 6 . Kevin is assigned to a software development project that will start in the near future and is currently tailoring the PMBOK processes
Kevin is assigned to a software development project that will start in the near future and is currently tailoring the PMBOK processes to satisfy the projects specific needs. Kevin wants to introduce a new process, Identify Key Deliverables to the existing six project scope management processes. Although he understands that project deliverables identification is already in the PMBOK scope management processes, he believes that having a dedicated process will stress the importance of determining and agreeing to key project deliverables. The best position for the new Identify Key Deliverables process should be between which of the following two processes?