Question: 1 7 A project management organization is preparing a network for one of the projects that it has recently bid for. The client demands that

17 A project management organization is preparing a network for one of the projects that it has recently bid for. The client demands that the project needs to be completed and delivered at its site by Week 25. The organization has identified the list of activities to be performed and estimated the duration of each of the activities. The details are given in the table below. Use this information to draw a network and help the organization answer the following questions.
Activity
Predecessor
Duration (weeks)
8
A
B
A
3
C
A
6
D D
A
4
E
B
5
F
B
4
G
H
C,E
D
6
1
6
J
6
K
D
4
G,H,I
J,K
3
L
3a) Will the organization be able to meet the customer's deadline of 25 weeks?b) If the organization cannot, identify the set of activities that need to be considered for a possible reduction in duration.c) If the cost of reduction of duration is INR 10,000 per week and the organization will have to pay a penalty of INR 7,000 per week of delay in completion in addition to paying a fixed amount of INR 20,000, what will your recommendation be to the organization with respect to reducing the duration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!