Question: 1 7 . What will result from an increase in the risk - adjusted discount rate for an average risk project? a . no change
What will result from an increase in the riskadjusted discount rate for an average risk project?
a no change in the NPV
b a decrease in the IRR
C an increase in the NPV
d a decrease in the NPV