Question: 1 7 . You are the project manager at an industrial design firm. You expect to spend a total of 5 on your current project.
You are the project manager at an industrial design firm. You expect to spend a total of on your current project. Your plan calls for six people working on the project eight hours a day, days a week for four weeks. According to the schedule, your team should have just finished the third week of the project. When review what the team has done so far, you find that they have completed of the work, at a cost of TL Which of the following BEST describes your project?AYour project is ahead of schedule and under budget BYour project is behind schedule and over budgetCYour project is behind schedule and under budget DYour project is ahead of schedule and over budget