Question: [ 1 8 : 5 9 , 0 2 / 1 0 / 2 0 2 4 ] Archit Sharma: Following are the project activities
: Archit Sharma: Following are the project activities and dependencies undertaken during the community health clinic upgrade project:
Facility Renovation Preparation:
Duration: days
Predecessor. None Starts first
Facility Renovation:
Duration: days
Predecessor: Facility Renovation Preparation
Health Information System Selection:
Duration: days
Predecessor. None Can start simultaneously with Facility Renovation Preparation
Health Information System Implementation:
Duration: days
Predecessor: Facility Renovation, Health Information System Selection
: Archit Sharma: Medical Equipment Selection:
Duration: days
Predecessor: Facility Renovation
Medical Equipment Upgrade:
Duration: days
Predecessor: Medical Equipment Selection, Health Information System Implementation
Staff Training on New Systern:
Duration: days
Predecessor. Health Information System Implementation
Final System Testing:
Duration: days
Predecessor. Medical Equipment Upgrade, Staff Training on New System
Public Relations Campaign:
Duration: days
Predecessor: Health Information System Selection Begins after selecting the system to start generating buzz
: Archit Sharma: Grand Reopening Preparation:
Duration: days
Predecessor: Final System Testing
: Archit Sharma: Calculate the Project's Critical Time: Add the durations of all tasks within the critical path to find the total time required for project completion
: Archit Sharma: Compute the Float for Noncritical Activities: Establish the early start, early finish, late start, and late finish for each task to calculate the float or slack time, showing how much delay is tolerable for noncritical tasks without affecting the overall project timeline.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock