Question: 1 8 A 2 - cy dragline with a standard short boom is operated at 6 0 % optimum depth of cut and a 7

18 A 2-cy dragline with a standard short boom is operated at 60% optimum
depth of cut and a 75-degree angle of swing. It is used to excavate moist
10am. The average bucket load, expressed in bcy, can be taken to be 0.85
of the struck capacity, cubic feet listed, as listed in Table 9.16. On the
assumption that the data from Tables 9.14 and 9.15 are applicable,
calculate the peak rate cycle time for the dragline in minutes.

Step by Step Solution

There are 3 Steps involved in it