Question: 1 . ( 8 points ) Regular tires are made on one production line, and the other types of tires are made on a separate
points Regular tires are made on one production line, and the other types of tires are made on a separate line. On the regular tire production line, the bottleneck resource can produce pallets of tires per week without failures. It fails on average every hours, and it has an average time to repair of hours.
a What is the minimum number of servers needed at the bottleneck station to keep utilization under on average?
b Assume interarrival CV is natural process time CV is and repair time CV is Given the number of servers, what are longrun cycle time, throughput and WIP?