Question: 1. A common goal in designing process layouts is: Select one: a. Minimizing the number of workers b. Minimizing idle time c. Minimizing material handling
1. A common goal in designing process layouts is:
Select one:
a. Minimizing the number of workers
b. Minimizing idle time
c. Minimizing material handling costs
d. Balancing the work at each station
e. Maximizing inputs
2. In Line balancing, the more idle time we have, the better the efficiency of the Production line.
Select one:
a. True
b. False
3. Cycle time is:
Select one:
a. Operating time divided by desired production
b. The maximum allowable time at each work station
c. The available time that can be used to produce a unit from a product
d. all of the above
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts