Question: 1 . A compacted fill is being built with 2 sheep's - foot c File Preview s that each have a 5 - ft wide

1. A compacted fill is being built with 2 sheep's-foot c File Preview s that each have a 5-ft wide drum, operating at \(2.0\mathrm{mi}./\mathrm{hr}\). Six passes are required to obtain the \(6-\mathrm{in}\). depth of compacted fill to meet the moisture/density specifications. A spread of 22-cy, loose measure, trucks will haul the fill dirt to the compacted area. Analysis of the soil conditions indicates a 22-cy loose measure truck is equivalent to 15.8 cy compacted measure. Determine number of trucks and compactor drums are required.
A) If the cycle time of a single truck is 15 min ., how many trucks are required?
B) If 130,000 cy of compacted fill are required using this compaction equipment, how many drums are required if the project is to be completed in 28 days?
2. An equipment operator is estimated to work, 10 hours/day and 5 days/week, with typical overtime rates. The equipment works the same hours per day as the operator with an equipment cost of \(\$ 115/\) hour and can move up to 50 cy/hour. Apply a productivity of 45 minutes per hour. Calculate the amount of material that can be moved in a week. Find the production unit cost per hour for earthmoving equipment and its operator based on cubic yards.
1 . A compacted fill is being built with 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!