Question: 1) A construction company has 5 projects. The contract amount of each project is as follows: Project 1: $1,000,000 Project 2: $2,000,000 Project 3: $1,500,000
1) A construction company has 5 projects. The contract amount of each project is as follows: Project 1: $1,000,000 Project 2: $2,000,000 Project 3: $1,500,000 Project 4: $1,200,000 Project 5: $ 800,000 The total overhead of this company is $120,000. Determine the overhead allocated to each of the projects if the contract amount is the allocation base. (20 points)
2) The controller decides to interview key managers of the Manufacturing, Design, and Quality departments.
The results are:
| Department | overhead | costdriver |
| manufacturing | 100000 | machine hours |
| design | 54000
| No. of drawing sheet |
| quality | 120000 | No. of inspection |
Details regarding the usage of cost drivers for 3 contracts are:
Department Cost driver A B C
Manufacturing Machine hours 560 450 290
Design Number of Drawing Sheet 80 70 100
Quality Number of Inspection 160 155 190
- What is the overhead cost rate for each department? (10 points)
- What is overhead costs allocated to each contract? (10 points)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
