Question: 1. a) Define Scope, as it relates to a project. (5 pts) b) Explain the use of supporting documents in project scope management. (10 pts)
1. a) Define Scope, as it relates to a project. (5 pts)
b) Explain the use of supporting documents in project scope management. (10 pts)
2. The following table indicates the activity, and time duration of each task in the development of a project:
| Activity | Description | Duration (Days) | Immediate Predecessor |
| A | Requirement Analysis | 5 | - |
| B | System Design | 15 | A |
| C | Implementation | 25 | B |
| D | Telecommunication | 15 | B |
| E | Equipment Installation | 30 | B |
| F | System Integration | 10 | C, D |
| G | System Testing | 10 | E, F |
| H | Training | 5 | G |
| I | System Deployment | 5 | H |
a) Draw the network for the information provided in the table (12 pts.)
b) Determine (specify) all paths through the network (9 pts.)
c) Determine the Critical Path(s) (7 pts.)
d) Calculate the planned duration of the project (8 pts.)
e) Determine the ES, EF, LS, and LF for Activity A and Activity B, (24 pts.)
Activity 1: Activity 2:
ES =______________________ ES =____________________________
EF = _______________________ EF = ____________________________
LS = _______________________ LS = ____________________________
LF = _______________________ LF = ____________________________
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts