Question: 1. a) Define Scope, as it relates to a project. (5 pts) b) Explain the use of supporting documents in project scope management. (10 pts)

1. a) Define Scope, as it relates to a project. (5 pts)

b) Explain the use of supporting documents in project scope management. (10 pts)

2. The following table indicates the activity, and time duration of each task in the development of a project:

Activity

Description

Duration (Days)

Immediate Predecessor

A

Requirement Analysis

5

-

B

System Design

15

A

C

Implementation

25

B

D

Telecommunication

15

B

E

Equipment Installation

30

B

F

System Integration

10

C, D

G

System Testing

10

E, F

H

Training

5

G

I

System Deployment

5

H

a) Draw the network for the information provided in the table (12 pts.)

b) Determine (specify) all paths through the network (9 pts.)

c) Determine the Critical Path(s) (7 pts.)

d) Calculate the planned duration of the project (8 pts.)

e) Determine the ES, EF, LS, and LF for Activity A and Activity B, (24 pts.)

Activity 1: Activity 2:

ES =______________________ ES =____________________________

EF = _______________________ EF = ____________________________

LS = _______________________ LS = ____________________________

LF = _______________________ LF = ____________________________

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!