Question: #1. (a) Draw the CPM network (10 points) (b) Perform the CPM calculations (10 points) (c) Mark the critical path (10 points) (d) Complete the

#1. (a) Draw the CPM network (10 points) (b)
#1. (a) Draw the CPM network (10 points) (b) Perform the CPM calculations (10 points) (c) Mark the critical path (10 points) (d) Complete the table below. (10 points) (e) How much can be expanded without effecting subsequent activities? (10 points) (f) How many days of float does the contractor of F own? (10 points) ES EF LS LF TF FF IF Duration Depends Activity (days) on A 6 B 2 8 A D 5 A,B E 3 B F 6 DE G 5 C,D H 2 F G