Question: 1 . A project has been defined to contain the following list of activities along with their required times for completion. begin { tabular

1. A project has been defined to contain the following list of activities along with their required times for completion.
\begin{tabular}{|c|c|c|c|}
\hline Activity No. & Activity & Time (Weeks) & Immediate Predecessors \\
\hline 1 & Collect requirements & 2 & -\\
\hline 2 & Analyze processes & 3 & 1\\
\hline 3 & Analyze data & 3 & 2\\
\hline 4 & Design processes & 7 & 2\\
\hline 5 & Design data & 6 & 2\\
\hline 6 & Design screens & 1 & 3,4\\
\hline 7 & Design reports & 5 & 4,5\\
\hline 8 & Program & 4 & 7,7\\
\hline 10 & Test and document & 8 & 8,9\\
\hline
\end{tabular}
a. Draw a network diagram for the activities.
b. Calculate the earliest expected completion time.
c. Show the critical path.
d. What would happen if activity 6 were revised to take 6 weeks instead of 1 week?
1 . A project has been defined to contain the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!