Question: 1. A project is being analyzed with below activities identified. Activities A and B start on day 0. Activity Duration (Days) Immediate Predeccesors a. organize
1. A project is being analyzed with below activities identified. Activities A and B start on day 0.
| Activity | Duration (Days) | Immediate Predeccesors |
| a. organize layout team | 3 | |
| b. organize modification team | 6 | |
| c. design personnel jobs | 6 | a |
| d. set machinery in place | 4 | b |
| e. connect utilities | 7 | c,d |
| f. modify conveyor system | 4 | e |
| g. train personnel | 5 | e |
| h. finishing touches | 4 | f |
| i. run test lot | 3 | g |
- Find ES, EF, LS, LF, and Slack values all activities.
| Activity | ES | EF | LS | LF | Slack |
| a | 0 | 3 | 1 | 4 | 1 |
| b | 0 | 6 | 0 | 6 | 0 |
| c | 3 | 9 | 4 | 10 | 1 |
| d | 6 | 10 | 6 | 10 | 0 |
| e | 10 | 17 | 10 | 17 | 0 |
| f | 17 | 21 | 17 | 21 | 0 |
| g | 17 | 22 | 17 | 22 | 0 |
| h | 21 | 25 | 21 | 25 | 0 |
| i | 22 | 25 | 22 | 25 | 0 |
- What is (are) the critical path(s)? b-d-e-f-h & b-d-e-g-i
- What is expected project duration? The expected project duration is 25 days
- If activity A is delayed by 1 day, what is new expected project duration?
4. If activity D is delayed by 1 day, what is new expected project duration?
already did most of it, just need help with 3 AND 4. also a check up on the other work would be appreciated
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts