Question: 1. A project is being analyzed with below activities identified. Activities A and B start on day 0. Activity Duration (Days) Immediate Predeccesors a. organize

1. A project is being analyzed with below activities identified. Activities A and B start on day 0.

Activity Duration (Days) Immediate Predeccesors
a. organize layout team 3
b. organize modification team 6
c. design personnel jobs 6 a
d. set machinery in place 4 b
e. connect utilities 7 c,d
f. modify conveyor system 4 e
g. train personnel 5 e
h. finishing touches 4 f
i. run test lot 3 g

  1. Find ES, EF, LS, LF, and Slack values all activities.

Activity ES EF LS LF Slack
a 0 3 1 4 1
b 0 6 0 6 0
c 3 9 4 10 1
d 6 10 6 10 0
e 10 17 10 17 0
f 17 21 17 21 0
g 17 22 17 22 0
h 21 25 21 25 0
i 22 25 22 25 0

  1. What is (are) the critical path(s)? b-d-e-f-h & b-d-e-g-i
  2. What is expected project duration? The expected project duration is 25 days
  3. If activity A is delayed by 1 day, what is new expected project duration?

4. If activity D is delayed by 1 day, what is new expected project duration?

already did most of it, just need help with 3 AND 4. also a check up on the other work would be appreciated

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!