Question: 1. A project manager discovers that a project problem has occurred. The problem was never discussed during risk planning activities or added to the risk

1. A project manager discovers that a project problem has occurred. The problem was never discussed during risk planning activities or added to the risk register and it will cost the project money. What is the best response?

a) Add the risk to the risk register and gather information about its probability and impact.

b) Use the management reserve to cover the costs of the problem.

c) Stop all project activity and approach senior management for advice.

d) Dont take any action, just accept that theres a problem that the team did not plan for.